Manage and filter Revit phases when you import a model into SketchUp. Phases track when building elements are built or demolished. Each view represents a point in time, and walls or doors you add take that view's date.
How phases track element status
Revit uses two properties to track the construction status of elements over time:
- Phase Created shows when an element was added to the model.
- Phase Demolished shows when an element is removed. It stays blank if the element is never removed.
Each phase tracks elements using these statuses:
- Existing means an element was created in an earlier phase and still stands in the current phase.
- Demolished means an element was created in an earlier phase and demolished in the current phase.
- New means an element was created in the current phase.
- Temporary means an element was created and demolished in the current phase.
Phases in the Revit Importer
The Revit Importer may show these phase options:
- New Construction
- Existing
- Demolished
- Temporary
Excluding the Demolished phase may leave demolished elements from your .rvt file in the import. These elements can also appear in the Existing and New Construction phases. To exclude all demolished elements when importing, set Revit's Phase Filter to Show Complete:
- In Revit, open the 3D view you want to import.
- With nothing selected in your file, open View Properties.
- Find the Phase Filter property and select Show Complete.
- Save your file.